Queenstown Cable Car Route Revised After Community Feedback

Southern Infrastructure Limited adjusts cable car design to address local concerns regarding Frankton.

Newstalk ZB2 min

1Revised Infrastructure Design

Southern Infrastructure Limited has officially modified the proposed cable car route in Queenstown following extensive community feedback. The updated design shifts the path to run alongside the Queenstown Events Centre instead of crossing its playing fields. This change aims to preserve local recreational space while maintaining the project's overall connectivity goals.

2Community Engagement Process

The refinement process involved months of collaboration with residents, local businesses, and the Queenstown Lakes District Council. Engagement efforts included four public webinars and a community survey that gathered nearly 900 responses. These interactions highlighted specific concerns regarding land use and the impact of the proposed route on existing public facilities.

3Strategic Station Placement

The four new Frankton stations are now aligned with the council’s Te Kirikiri/Frankton Masterplan. Locations include Frankton Village, Queenstown Airport, the Five Mile Urban Corridor, and Quail Rise. By positioning these hubs within identified precincts, the developers aim to integrate the cable car system more effectively into the existing local transport network.

4Intermodal Transport Integration

A key feature of the revised plan is the repositioning of the Frankton interchange to connect directly with the existing Frankton Bus Hub. This station will be located above the golf course car park, facilitating seamless transfers for commuters. The design prioritizes accessibility for residents, workers, and visitors across the region.

5Addressing Southern Corridor Concerns

Despite the updates, residents in southern suburbs like Jacks Point and Hanley’s Farm expressed concerns about ongoing traffic congestion. Chief executive Ross Copland acknowledged these issues, noting that current plans focus on the Town Centre and Ladies Mile lines. The company is now investigating options to accelerate transport solutions for these areas.

6Future Project Timeline

The revised alignment will be submitted to the council in December 2026 for review. A fast-track application is anticipated in the first quarter of 2027, with a final decision expected by the end of that year. Construction for the network is currently scheduled to take place between 2028 and 2030.

7Operational Design Goals

The project aims to serve areas where Queenstown is projected to grow, including residential and commercial zones. By connecting the airport, shopping corridors, and cycle routes near the Shotover River, the network seeks to reduce reliance on private vehicles. Station locations remain indicative and are subject to further detailed design and approvals.

8Context of Infrastructure Development

Large-scale infrastructure projects in growing tourist hubs often face significant scrutiny regarding land use and traffic impact. The Queenstown cable car proposal reflects a broader effort to modernize public transit in the region. Balancing community feedback with engineering requirements remains a critical challenge for developers throughout the planning and construction phases.

Original article: Newstalk ZB — Queenstown Cable Car Route Revised After Community Feedback