Drax Proposes Massive £20 Billion AI Datacenter at North Yorkshire Site

Energy giant Drax partners with Brookfield to transform its biomass plant into AI infrastructure.

5 sources3 min

1Ambitious AI Infrastructure Plan

Drax has unveiled plans for a £20 billion AI datacenter development at its North Yorkshire biomass power station. Partnering with investment firm Brookfield and its subsidiary Radiant, the project aims to eventually exceed one gigawatt of capacity. This initiative seeks to repurpose existing energy infrastructure to support Britain's growing AI ambitions.

2Phased Development Strategy

The project is structured in three distinct phases starting in early 2028. The initial phase targets 100MW of capacity with a £2.5 billion investment. A second phase aims to add 500MW between 2028 and 2031, with further expansion beyond 1GW planned thereafter, contingent on finding anchor tenants and securing regulatory approvals.

3Leveraging Existing Grid Access

Drax highlights its 1,000-acre site as a strategic asset due to its 4GW of grid access and 2.6GW of active generation capacity. By utilizing existing infrastructure, the developers hope to bypass the grid connection queues that have delayed other UK datacenter projects, such as the previously reported Microsoft-linked Nscale site.

4Direct Power Supply Goals

While the first phase draws from the national grid, Drax intends to supply up to 500MW directly from its own generators by the early 2030s. This requires government consent to redirect biomass capacity under a long-term power purchase agreement, balancing energy security needs against the site's future operational limitations.

5Sustainability and Carbon Concerns

Analysts identify the Drax plant as the UK's largest carbon dioxide emitter, though the government excludes these emissions based on biomass sustainability claims. With subsidies set to halve between 2027 and 2031, this datacenter project represents a critical pivot for the company to secure long-term revenue and site viability.

6Regulatory and Planning Hurdles

The proposal faces significant obstacles, including the need for planning permission, network approvals, and final investment decisions. Drax must also navigate public consultations starting this month. Previous attempts to develop the site, including a 1.2GW AI Growth Zone proposal involving the University of York, were previously rejected by authorities.

7Government and Economic Context

The UK government views datacenters as fundamental economic infrastructure, recently labeling them as vital as railways. Treasury official Emma Reynolds welcomed the investment as a driver for reindustrialization and job creation. However, the project arrives amid growing public opposition regarding the environmental impact and electricity consumption of large-scale server farms.

8Future Market Implications

Following the announcement, Drax's market value rose nearly 9% on the London Stock Exchange. The project's success depends on balancing the urgent demand for sovereign AI capability with strict climate targets. Whether this site becomes a model for repurposing legacy energy assets remains a key question for the UK energy system.